Who decides planning in Reigate
Reigate & Banstead Borough Council is the planning authority for Reigate, Redhill, Horley, Banstead and the villages in between. Applications go in through the Planning Portal or the council’s own website, and every past decision is searchable on the council’s planning register.
Surrey’s borough and district councils are due to be replaced by two new unitary councils, with Reigate falling under the eastern one. Until the switch happens the borough council deals with planning. After it, the Planning Portal will point you to whoever handles your postcode.
What permitted development lets you build
Permitted development rights let a house be extended within set limits without a planning application. The limits are measured against the “original house”, meaning the house as first built, or as it stood on 1 July 1948 if it’s older. Anything a previous owner added counts against your allowance.
The main limits for a house (not a flat) in England are below. They come with conditions on height, materials and distance from boundaries, so read the government’s technical guidance before you rely on a number.
- Single-storey rear extensions up to 3m deep on an attached house, or 4m on a detached one, and no more than 4m high.
- Larger single-storey rear extensions, up to 6m or 8m, through the prior approval route, where the council asks your neighbours for comments first.
- Single-storey side extensions up to half the width of the original house.
- Loft dormers adding up to 40 cubic metres on a terraced house, or 50 on a semi or detached one, and never on a roof slope that faces the road.
- Extensions and outbuildings together covering no more than half the land around the original house.
Where permitted development doesn’t apply
Permitted development isn’t a right every house has. Check these before anyone draws anything.
- Flats and maisonettes have no householder permitted development rights at all.
- Listed buildings need listed building consent for most changes, inside as well as out.
- In a conservation area, side extensions, two-storey rear extensions, roof extensions and external cladding all need planning.
- An Article 4 direction can remove specific rights in a particular street or area.
- Many newer estates were approved with a condition removing permitted development rights. It sits in the original planning permission, so check the planning history for your address.
Reigate’s conservation areas and listed buildings
Reigate has several conservation areas, including much of the old town around the High Street, and a good number of listed buildings. The council publishes a map of the boundaries. Historic England’s National Heritage List will tell you in a minute whether your house is listed.
Inside a conservation area the rules aren’t a ban, they’re a lower threshold. A rear extension may still go ahead under permitted development, but anything visible from the road or touching the roof usually needs an application, and the council will look closely at materials.
Green Belt around the edges of town
Much of the land around Reigate is Metropolitan Green Belt. Permitted development rights still apply to a house in the Green Belt, which surprises people. Where you need a planning application, though, the council will ask whether the extension is out of proportion to the original building, and that’s judged on size added over time, not just this one job.
If your house has already been extended once or twice, raise it early. It can decide what’s realistic.
How to check before you build
Five checks, roughly in this order, will tell you most of what you need.
- Search the National Heritage List to see whether the house is listed.
- Check the council’s conservation area map and any Article 4 directions.
- Search the planning register for your address and read the conditions on the original permission.
- Use the Planning Portal’s interactive house guide to see which limits apply to your extension.
- If you want it in writing, apply for a Lawful Development Certificate. It isn’t compulsory, but a buyer’s solicitor may ask for one later.
Planning is only half the paperwork
A job that doesn’t need planning will almost always still need building regulations approval, and work on a shared wall can bring in the Party Wall Act. The building regulations guide and the party wall guide cover both. If the property is outside Reigate, Builders in Surrey explains how the councils differ.